Over the course of the next 6 months all of the buildings in the park will be painted. Below is a schedule of the order in which they will be painted and the estimated time frame for each building. During the time that your building is being painted different sections of your parking lot may be blocked off. We realize that this may be an inconvenience and we will do our best to minimize it.
Building 6 – 3600 : Start date: 10/24-11/12/22
Building 1 - 3998: Estimate start date: 11/12-11/29/22
Building 2 - 3848: Estimated start date: 11/26-12/14/22
Building 3 - 3701: Estimated Start date: 12/11-12/28/22
Building 4 - 3651: Estimated start date: 12/27-1/14/23
Building 5 - 3731: Estimated start date: 1/14-1/31/23
Building 7- 3231: Estimated start date: 2/4-2/28/23
If you have any questions please don’t hesitate to ask.
Thank you and have a great day
Pam
Pam Lunsford-Ashworth | Real Estate Services Administrator
CBRE | Property Management
3998 FAU Boulevard, Suite 120 | Boca Raton, FL 33431
T 561.409.2035 x203 | F 561.756.8648